3 Deliverables Achieved at Shcneider Electric

Schneider Electric | Case Study

At Schneider Electric’s Dubai office in Silicon Oasis, the need for space flexibility met head-on with high acoustic and design expectations. The goal was straightforward: take a large open area and turn it into four smaller, functional spaces with a clear corridor pathway in between. But as we all know, even the most straightforward plans come with their share of complications, especially when you’re working with high-end finishes, strict municipal regulations, and tight tolerances.

Biggest Obstacle of The Project

25mm Finishes Sound Simple, Until They break everything

Thick finishes were a requirement to create a visual impact. We had to find a way to keep acoustic performance intact and meet the local authority’s requirement on door widths.

Biggest Obstacle of The Project

Re-Engineering a Pass Door while Keeping the Design Intact

A 915mm Clearance Was Non-Negotiable, So We Got Creative

The main pass door had to double as a corridor entrance.
But with the thick finishes, we were falling short of the mandated
clearance.

Re-Engineering a Pass Door while Keeping the Design Intact

Full Solution and How we Made it Work

We Didn’t Just Install, We Redesigned it to Work Smart

The main pass door had to double as a corridor entrance.
But with the thick finishes, we were falling short of the mandated
clearance.

Full Solution and How we Made it Work

About Gibca

GIBCA has been at the forefront of architectural innovation for decades, offering world–class products and solutions across the Middle East. With a commitment to quality, design, and customer satisfaction, GIBCA continues to set benchmarks in the construction and design industry. Our pivot door solutions embody this ethos, combining durability, functionality, and timeless aesthetics.